Can a journal report be used to track how many times an individual task date is adjusted?

@skyehansen I saw you post this link on journal entry reports and it got me thinking on another report I'd like to see... Can a journal report be used to track how many times a planned completion date was changed on a project? Or would it just show the project's planned completion date adjusting accordingly? Thanks!

skyehansen
skyehansenAccepted solution
Feb 12, 2024 4:19 PM UTC

I'm not sure what you mean by "adjusting accordingly" but just as you can track project completion dates, you can also track task completion dates similarly. You would just have to adjust the filter to look for tasks rather than projects? Hope I read your question right.

2 replies

skyehansen
Adobe Champion and Community Advisor
skyehansenAdobe Champion and Community AdvisorAccepted solution
Feb 12, 2024 4:19 PM UTC

I'm not sure what you mean by "adjusting accordingly" but just as you can track project completion dates, you can also track task completion dates similarly. You would just have to adjust the filter to look for tasks rather than projects? Hope I read your question right.

Translate
Daniel_Clarke
Adobe Champion and Community Advisor
Adobe Champion and Community Advisor
Feb 12, 2024 5:47 PM UTC

Thanks for the confirmation! 