Skip to main content
Level 5
May 16, 2017 5:55 PM UTC
Delivered

Calendars -- Ability to Use Custom Form Date Fields

The calendars seem very limited in their options and therefore we haven't been able to use them effectively as everyone would like.

It would be great if they could be used in conjunction with date fields in the custom forms instead of just the built-in planned, actual, projected dates on projects, tasks, and issues.

For example, we have custom form field for date of deployment for our email marketing campaigns. It would great to have those feed into a calendar.

18 replies

Level 9
Aug 1, 2017 5:46 PM UTC

Calendars are limited and practically useless to us, as it is designed. To use custom form date fields would be awesome.

Translate
Level 2
Feb 2, 2018 6:45 PM UTC

This would be a great feature. We are still reliant on using excel for our editorial calendar because of this limitation. Very frustrating.

Translate
Heather_Kulbacki
Community Advisor
Community Advisor
Mar 15, 2018 1:42 PM UTC

Additionally, it would be great to be able to use multiple custom form dates as a duration on a calendar.

Translate
Level 3
Sep 20, 2018 7:49 PM UTC

This would be a huge benefit to us. I notice this is now very close to the 45 vote threshold. Let's hope we carry this one to 45!

Translate
Level 6
Sep 20, 2018 8:44 PM UTC

one more !

Translate
Level 10
Sep 21, 2018 1:10 PM UTC

It would actually be good if you could use any date field and stick to it. Right now you can't even used Planned dates as they change to Actual dates once the project starts moving, so if someone doesn't click their "done" button correctly, the calendar becomes useless.

Translate
Level 3
Sep 21, 2018 2:28 PM UTC

I agree. All date fields should be eligible.

Translate
MattMa2Author
Level 5
Sep 21, 2018 2:31 PM UTC

Above 45 votes!



Translate
Nov 12, 2018 3:07 PM UTC

Totally agree, and voting for this as well!

Currently with the calendar we can pull the dates when our teams work on projects (which helps with capacity planning), but we can't pull the campaign start and end dates, which would be critical for us to have for campaigns panning.

Thanks!

Translate
Kelly_Wehrmann
Level 9
Mar 21, 2019 4:56 PM UTC

What is the status of this? I check on these from time to time and on 10/11/18 I have a note that the status was "under consideration".