Besides Fusion, does anyone know of a way to bulk edit the planned start date on Tasks?

I have tried in the timeline and in a report. In both places only the actual dates are on option to edit.

Thanks!

lgaertner
lgaertnerAccepted solution
Level 9
Mar 19, 2024 2:23 PM UTC

Hello Michael,

 

Before being able to bulk edit planned start dates on task, you need to make sure, that all tasks are set to a task constraint, which allows editing the planned start date.

 

If you select multiple  tasks and click on edit, changing the Task constraint to e.g. "Fixed Dates" will provide you with the possibility to change the planned start & end date. 

 

Regards

Lars

2 replies

lgaertner
lgaertnerAccepted solution
Level 9
Mar 19, 2024 2:23 PM UTC

Hello Michael,

 

Before being able to bulk edit planned start dates on task, you need to make sure, that all tasks are set to a task constraint, which allows editing the planned start date.

 

If you select multiple  tasks and click on edit, changing the Task constraint to e.g. "Fixed Dates" will provide you with the possibility to change the planned start & end date. 

 

Regards

Lars

Translate
Level 2
Mar 19, 2024 3:47 PM UTC

Thank You! Changing the constraint did make the field appear. 