Hello! I am wondering if it is possible to have tasks auto complete if there is a role attached to it. I attached an example of the current task setup that I have. We do not want to assign the role as we use a project for a workaround to be able to track resources. Thanks in advance!

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Richard_Le_

Hi,

 

It is possible to have Workfront auto-complete tasks when they reach the planned completion date (see article here), but it's not possible to do this conditionally (i.e., only if a role is assigned) using the native functionality in the system.

 

This could, however, be achieved with Fusion. 

 

Best Regards,

Rich. 

2 replies

Richard_Le_
Community Advisor
Richard_Le_Community AdvisorAccepted solution
Community Advisor
February 21, 2023

Hi,

 

It is possible to have Workfront auto-complete tasks when they reach the planned completion date (see article here), but it's not possible to do this conditionally (i.e., only if a role is assigned) using the native functionality in the system.

 

This could, however, be achieved with Fusion. 

 

Best Regards,

Rich. 