Skip to main content
Level 2
Mar 29, 2017 7:21 PM UTC
New

Allow “Mass Collapse” of all parent tasks that are 100% complete

Allow “Mass Collapse” of all parent tasks that are 100% complete

We have large projects that can be thousands of lines long. As a general rule, there is not a daily need to look at the fine details of completed work. I can spend many minutes collapsing all completed tasks to whittle down to a view that shows me the remaining work. Given that workfront does not save the state of my collapsed tasks, I have to do this over and over again throughout the project in order to make the project readable (and speed up the display). I don’t want to use a filter to remove completed tasks as it is beneficial to see tasks in the context of the whole project. It would be nice to have a ‚Äòmass collapse’ feature that allows me to one-click collapse all parent tasks at 100% complete.

12 replies

Level 2
Aug 29, 2017 12:47 PM UTC

completely agree and I hope they fix this soon

Translate
Oct 4, 2018 2:17 PM UTC

agree

Translate
Level 10
Dec 19, 2019 3:36 PM UTC

Our task lists are much shorter, so I never would have thought of this kind of "auto collpase"...and wow, what a great idea and a nice QoL suggestion!

Translate
Level 2
Dec 20, 2019 2:18 PM UTC

That's a great Idea!

Translate
Level 2
Mar 6, 2020 4:37 PM UTC

I agree and in addition would like to be able to save any view I have set collapsing some rows but not all.

Translate
Level 6
Jul 29, 2020 2:51 PM UTC

I have an idea posted that kinda goes along with this for storyboard views.... this would be great too. UPVOTE!!


https://one.workfront.com/s/idea/0870z000000XiMrAAK/detail

Translate
Level 2
Jul 29, 2020 7:26 PM UTC

This is an awesome idea.

Translate
Level 2
Oct 22, 2020 3:52 PM UTC

Big time saver

Translate
Level 2
Jun 15, 2021 6:33 PM UTC

While I do not work with thousands of lines of tasks like Scott, my studio adds multiple batches of tasks over time and this feature would definitely be helpful in keeping our projects cleaner. As batches are completed we could collapse select groups of tasks to leave the focus on the current/open tasks only. Would love to see an option for this implemented!

Translate
Level 10
Nov 12, 2021 7:08 PM UTC

Just an FYI - this can currently be accomplished by using a Filter called "Incomplete Tasks" or whatever you want to call it. The Text Mode code for it is:


statusEquatesWith=CPL

statusEquatesWith_Mod=ne


I think this accomplishes what you're asking (unless there's a piece I'm missing).

Translate