Skip to main content
Level 2
October 9, 2024
Question

Workload balancer and planned hours for tasks with multiple users assigned

  • October 9, 2024
  • 1 reply
  • 488 views

When multiple resources are assigned to a particular task, how do you ensure accurate planned hours are rolling up into the workload balancer for each resource for that task?

Thank you!

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Rafal_Bainie
Community Advisor
Community Advisor
October 10, 2024

you can define this in Advanced allocations/assignments:

you define Planned Hours per resource:

this window is also available from Workload balancer view, hold CTRL and click on the task and select advanced as above