Is there a way to change all the dates for tasks in an Agile project to the end date and not the start date of the project?

  • February 26, 2021
  • 1 reply
  • 440 views

When creating an Agile project, the tasks default to the start date of the project. I would like to set the tasks and any consecutive tasks to take on the end date of the project or 1st sprint of the project.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

March 3, 2021

The closest you could get to this would be to change Schedule Mode for the Project to be based on Completion Date, or just bulk edit the tasks and change Task Constraint to Must Finish On and manually set the date.