Is it possible to retain cross-project predecessors if I create a copy of a project that has those cross-project predecessors already built in? | Community
Skip to main content
Level 4
March 27, 2021
Question

Is it possible to retain cross-project predecessors if I create a copy of a project that has those cross-project predecessors already built in?

  • March 27, 2021
  • 1 reply
  • 464 views

I am finding that when I create a copy of a project, those cross-project predecessors don't flow through to the copied project (but all other normal predecessors do copy over). Is there a setting where we can keep the cross-project predecessors as well?

Thank you!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
March 27, 2021

Spoooooky Olivia,

None that I know of (having just looked again this week), so I just green-lighted an R&D project to develop that functionality for one of my clients this afternoon.

If you find out otherwise (or anyone else knows better), please let me know.

Regards,

Doug

OliviaMiAuthor
Level 4
March 29, 2021

Thanks Doug!