Is it possible to retain cross-project predecessors if I create a copy of a project that has those cross-project predecessors already built in? | Community
Skip to main content
Level 4
March 27, 2021
Question

Is it possible to retain cross-project predecessors if I create a copy of a project that has those cross-project predecessors already built in?

  • March 27, 2021
  • 2 replies
  • 477 views

I am finding that when I create a copy of a project, those cross-project predecessors don't flow through to the copied project (but all other normal predecessors do copy over). Is there a setting where we can keep the cross-project predecessors as well?

Thank you!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
March 27, 2021

Spoooooky Olivia,

None that I know of (having just looked again this week), so I just green-lighted an R&D project to develop that functionality for one of my clients this afternoon.

If you find out otherwise (or anyone else knows better), please let me know.

Regards,

Doug

Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.
OliviaMiAuthor
Level 4
March 29, 2021

Thanks Doug!