How to create a "Task Ready to Start" report for a Team?

Individual users have immediate access to tasks that are ready to start via the home screen's filters. How do you create a report that offers visibility into tasks that are ready to start but assigned to a Team, not an individual user? The "Task : Ready" option doesn't seem to be the right filter element.

Ce sujet a été fermé aux réponses.

2 commentaires

Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
October 30, 2020

Hi Chris,

I’d suggest filtering for Assignment ID is null, Team ID is not null, and Handoff Date is not null.

Regards,

Doug

Level 2
February 1, 2024

try to filter by Task > Can Start = True