How can I create a report where task #2 is complete but task #3 is not? So I can create a list of the #3's that need completing?

  • July 21, 2020
  • 1 resposta
  • 447 Visualizações
No text available
Este tópico foi fechado para respostas.

1 Resposta

Level 3
July 22, 2020

Hi @Kendra Roberts‚ ,

Is this a task report? Have you tried the filter Task > Can Start >> True ? We use this filter so that our users know which task is ready for them to start working.