Hi community, I have a requirement to see last updated comment text in the task report | Adobe Higher Education
Skip to main content
February 6, 2024
Répondu

Hi community, I have a requirement to see last updated comment text in the task report

I am currently making a report, which will display the the tasks which is been completed, within the last 7 days, and also display the last comment for each of the task, any idea how to do the same.

Ce sujet a été fermé aux réponses.
Meilleure réponse par KellieGardner

You are trying to add a column that displays the last update made on the task? 

 

You should be able to use Last Note Note Text

 

 

1 commentaire

KellieGardner
Community Advisor
Community Advisor
February 6, 2024

You are trying to add a column that displays the last update made on the task? 

 

You should be able to use Last Note Note Text

 

 

VanishVeAuteur
February 6, 2024

Thanks for the answer this really help a lot.