For Project - Possible to track All Planned Completion Date which are changed
Is it possible to track all planned complation date of a project? And to list all Previous Planned Completion Date.
Any recommendation. Note: We do not have Fusion yet.
Is it possible to track all planned complation date of a project? And to list all Previous Planned Completion Date.
Any recommendation. Note: We do not have Fusion yet.
Hi Kundan,
You can track changes to the project planned completion date via update feeds. You can read more on this here.
When you enabled Project>>plannedCompletionDate as a tracked field, any change to this will record a system update in the updates area of the project. You could then report on this using a Journal Entry report which you can read more on here.
Best Regards,
Rich.