How do I change a set time

Hi

I have set a time for my email campaign but need to change the date it goes out. How do I do this?

Thanks
Este tópico foi fechado para respostas.

2 Respostas

September 5, 2013
If its a batch campaign, you would set the time and date in the same location, in the dialog box after clicking on Run Once:



If you have a different use case, please share more and we can point you in the right direction
Traduzir
September 5, 2013
I guess you have already scheduled it, but need to change the date, right?

Go to the schedule tab. Click on the red cross next the the scheduled batch to delete the next run. Now you can set a new date and time.

Traduzir