When you set up a wait step that "must end on", the action will not happen until the day it must end on.
 
So if a flow is triggered on Sunday the 1st (for example), and includes this wait step (below) the next action in the flow won't happen until Friday the 13th of the following week. Is that correct?Inline image 1
Thank you for your help!
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by
The image in this post is not displaying properly for me. But if your Wait step looks something like this:

Wait 1 week
     *Must end on Friday

then the answer to your question is yes.

2 replies

Accepted solution
May 6, 2013
The image in this post is not displaying properly for me. But if your Wait step looks something like this:

Wait 1 week
     *Must end on Friday

then the answer to your question is yes.
May 6, 2013
Oh sorry. The image actually shows "Until: 6 days and wait must end on Friday".