Sort Program Members by Success by date | Community
Skip to main content
Michelle_Tizian
Level 10
August 2, 2013
Solved

Sort Program Members by Success by date

  • August 2, 2013
  • 7 replies
  • 2212 views
I'm trying to track down the members of a particular program by success and date (date of success) or at least sort it by date, what's the best way to do this?  
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Michelle_Tizian

So I tried something else.  I created a smart list that has the following:

Member of program = true
Program is = program name
Success = true
When I view the leads I changed the default view and added acquisition date.  I couldn't really find success date.  But this works for me for now.  

7 replies

Josh_Hill13
Level 10
August 4, 2013
Will it let you add Success Date to the View and then sort?
August 5, 2013
I'm not seeing a value for success date that can be added to the view.  Michelle were you able to add this to your view?
Michelle_Tizian
Level 10
August 5, 2013
I tried a couple of times and I'm not seeing that option from creating a smart list.  I'll try to see if I can pull something from the analytics section.  
Michelle_Tizian
Michelle_TizianAuthorAccepted solution
Level 10
August 5, 2013

So I tried something else.  I created a smart list that has the following:

Member of program = true
Program is = program name
Success = true
When I view the leads I changed the default view and added acquisition date.  I couldn't really find success date.  But this works for me for now.  

Dan_Stevens_
Level 10
January 14, 2014
Michelle - I was just trying to do the same thing you were trying to do.  I found a field you can add to the "Members" view called "Member Date".  This then allows you to sort your view by the date they became members of the program.
Michelle_Tizian
Level 10
January 14, 2014
Thanks for the tip Dan.  I'll give that a try.  
Josh_Hill13
Level 10
February 14, 2014
Perhaps setting another trigger outside that says