My client wants a record of the date a lead became an MQL and I suggested we simply add a date field - "MQL Date" - and that I could have the campaign that changes Lead Status to MQL also set the MQL Date field to the current date. Great suggestion, right? Except now I can't figure out how to set the date field! Surely there is a way to have a flow step that sets a date field to "today" where "today" is whatever the current date is? Please help!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by

Use the {{system.dateTime}} token with a Change Data Value flow step.

1 reply

Accepted solution
August 13, 2015

Use the {{system.dateTime}} token with a Change Data Value flow step.

August 13, 2015

Thank you! I knew it had to be something simple like that.