Exam question - start and end data of the event

Why is the last answer correct?

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Mohan_Dugganab
Mohan_DugganabAccepted solution
Adobe Employee
Mar 17, 2025 3:27 PM UTC

In the unitary event, advanced rule can be created to check if the current date is between the start and end date ranges.

 

For the streaming segment, it has to follow one of the eligible query types mentioned in https://experienceleague.adobe.com/en/docs/experience-platform/segmentation/methods/streaming-segmentation#:~:text=Streaming%20segmentation%20is%20the%20ability,schedule%20and%20run%20segmentation%20jobs. 

2 replies

Mohan_Dugganab
Adobe Employee
Mohan_DugganabAdobe EmployeeAccepted solution
Adobe Employee
Mar 17, 2025 3:27 PM UTC

In the unitary event, advanced rule can be created to check if the current date is between the start and end date ranges.

 

For the streaming segment, it has to follow one of the eligible query types mentioned in https://experienceleague.adobe.com/en/docs/experience-platform/segmentation/methods/streaming-segmentation#:~:text=Streaming%20segmentation%20is%20the%20ability,schedule%20and%20run%20segmentation%20jobs. 

Translate
Level 2
Mar 24, 2025 10:45 AM UTC

Hi @michael_soprano ,

 

2nd option is incorrect, because your audience evaluation method is 'streaming', and with streaming segmentation, audience qualification now happens as streaming data lands into Platform, alleviating the need to schedule and run segmentation jobs.

 

4th option is correct, as you have the option to select event schema that includes start and end date. Select these fields while defining the event and the use these fields under split condition in journey.

 

 

Thanks,

Pankaj

 

 