Question

AJO Scheduler

  • August 25, 2026
  • 2 replies
  • 14 views

Hi there,

 

I have a Read Audience (RA) journey that needs to run twice over a 4-week period (it must remain on a 4-week schedule), and the business would like to include an additional one-day buffer before the journey ends. Should I configure the journey schedule as follows:

 

Scheduler Type: Weekly

Repeat every: 4

Start date: 25/08/2026 (10:00)

Repeat until: 23/09/2026 (16:00)

 

Thanks!

2 replies

SatheeskannaK
Community Advisor
Community Advisor
August 25, 2026

@AK5 Yes, it should run twice, as per the schedule mentioned.

  • 1st run: August 25, 2026
  • 2nd run: September 22, 2026

Thanks, Sathees
AK5Author
Level 2
August 25, 2026

Many thanks, Sathees!