Hi Team,

 

When ever we upload any asset DAM Update asset workflow will be called create meteData and renditions.

 

Need to know how that Process as been written for creating a rendition which takes and creating the images.

Where i can see and understand that  process code where it takes 

Thumbnail Arguments

and created renditions

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
SantoshSai
SantoshSaiAccepted solution
Community Advisor
Dec 6, 2021 8:45 PM UTC

2 replies

SantoshSai
Community Advisor
SantoshSaiCommunity AdvisorAccepted solution
Community Advisor
Dec 6, 2021 8:45 PM UTC
Kishore_Kumar_
Level 9
Dec 7, 2021 4:27 AM UTC

Hi @manikanthar1295 ,

 

Check in below bundle

Day Communique 5 DAM Core Implementation

and the below process

com.day.cq.dam.core.impl.process.ThumbnailProcess