Launching a workflow after DAM Update Asset

  • November 9, 2019
  • 1 reply
  • 1374 views

I've got a workflow model that I want to run after DAM update asset finishes without modifying the DAM update asset workflow itself. I know that DAM_UPDATE_ASSET_COMPLETED event triggers at the end of DAM update, but I'm not sure how I can leverage this in my Workflow Launcher conditions. Is this possible, or is the only way to do this by creating an event listener with the workflow model logic inside?

All help is appreciated.

Thanks

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by sunjot16

You can use Workflow Steps as follows:

Workflow Step Reference

1 reply

sunjot16
Adobe Employee
sunjot16Adobe EmployeeAccepted solution
Adobe Employee
November 11, 2019

You can use Workflow Steps as follows:

Workflow Step Reference