Pause or stop scheduled WS | Adobe Higher Education
Skip to main content
New Member
July 28, 2021
Resuelto

Pause or stop scheduled WS

  • July 28, 2021
  • 4 respuestas
  • 1535 visualizaciones

Hi,

 

I have a daily WS report (goes out as PDF) that I have scheduled for the team. Now I want to pause/ stop the report since it's no longer required. How to do that?

Este tema ha sido cerrado para respuestas.
Mejor respuesta de khurshid

You can go to Components > Scheduled Projects, select the Project from the list and hit "Delete" button.

4 respuestas

meghat43023313
Adobe Employee
Adobe Employee
July 29, 2021

@dasparomita1984  - To stop receiving the Scheduled Projects, you need to remove your email from the Recipients.

 

Go to Analytics > Components > Scheduled Projects> Edit scheduled project > Update

 

 

 

New Member
August 2, 2021
Really helpful for updating WS scheduled reports. Thanks!
khurshid
Adobe Employee
khurshidAdobe EmployeeRespuesta
Adobe Employee
July 29, 2021

You can go to Components > Scheduled Projects, select the Project from the list and hit "Delete" button.

Level 4
July 30, 2021

Hi,

 

Go to components ->scheduled projects->select the project and then hit delete the project.