Hi Community, 

I'm trying to create a report to pull sub-tasks with Blank resources, or Durations or Planned hours. The purpose of this report is to ensure project owners or PMs don't leave any sub-task blank during project planning. 

Below (screenshot) is the report I created but is not working as expected, is pulling parent task and sometimes it does NOT pull sub-task that has no resources, or durations or planned hours. 

Any help on what filters to apply will be much appreciated. 

Thanks 

 

 

Questo argomento è stato chiuso alle risposte.
Migliore risposta di Ryzan99

Hi. Have you tried including "Task > Number of Children" within both the first and last logic? Since you're using an OR statement, you also need to include the same filter (Task > Number of Children) in the other logic. Please refer to the example screenshot. I hope this solution helps you.

 

5 risposte

Ryzan99Risposta
Level 2
August 21, 2023

Hi. Have you tried including "Task > Number of Children" within both the first and last logic? Since you're using an OR statement, you also need to include the same filter (Task > Number of Children) in the other logic. Please refer to the example screenshot. I hope this solution helps you.

 

meshackOmAutore
Level 3
August 23, 2023

Thank you so much @ryzan99  and @kundanism , your input was very valuable and it works. Please see the filters I used as per your input. Your help is super appreciated. 

 

 

Regards,

Mesh 

Level 2
August 28, 2023

You're welcome, @meshackom.

Kundanism
Level 10
August 21, 2023

May be you can try this one. Please refer the attachment. Believe matches your requirement criteria.

meshackOmAutore
Level 3
August 23, 2023