Skip to main content
Level 9
September 24, 2020
解決済み

Report to identify cross-project dependencies

  • September 24, 2020
  • 2 の返信
  • 687 ビュー

Hi WF Community,

Does anyone know if it's possible to filer a report (e.g. task report) based on tasks that have cross-project predecessors?

Can't seem to find an appropriate field within a task report for cross-project dependencies.

Thanks.

Nick

このトピックへの返信は締め切られました。
ベストアンサー AdinaPi1

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

2 の返信

AdinaPi1回答
Level 9
September 24, 2020

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

NickVa7作成者
Level 9
September 25, 2020

That worked. Thanks, Adina!