I found that the “Predecessor complete” is showing Yes when a predecessor is not complete, here is an example of that on a project:Project = https://barclaysus.my.workfront.com/project/67ec012623b06b3f9d1b5d8eb0506c2d/tasksHere is a screenshot, where I brought in “Predecessor Complete” and “Can Star...