  • Hi, I'm receiving support from the WF team. For now we have found out that the problem is a corruption of a column: Project: Planned hours alignment. The Team is investigating on this.. KR Alice Gregnanin Design & Digital Resource Specialist , Design to Launch Artwork and Packaging Services (APS) Ph...

    Type

    Questions

    Views

    303

    Likes

    0

    Replies

    0
  • Hi all, from yesterday (22 Aug 2019) I'm not able to see tasks list from my project page even if I have a System Administrator access. This is causing big issues...anybody faced this problem? Due to the contract I'm not able to use on line or live chat support. I've tried to send an email on the inf...

    Type

    Questions

    Views

    303

    Likes

    0

    Replies

    5
  • Thank you SKye! looks like the "assignment" was the real issue, so just picking "Assigned To" looks now correct! thank you all for the support Alice Gregnanin GSK

    Type

    Questions

    Views

    523

    Likes

    0

    Replies

    0
  • Hi Skye! The tasks are shared by more than one user for the most part so your suggestion is absolutely meaningful. Pls find attached the final resutl. The issue is I can see more hours respect the filtered ones. Thanks again Alice Gregnanin GSK

    Type

    Questions

    Views

    523

    Likes

    0

    Replies

    0
  • Hi All, need your help for a report that's driving me crazy. I have a team of selected users and I need to create a dashboard to show in the next 30 days how busy they are considering the planned hours on them all. I share the report details in a document. I don't know why the filtering is not worki...