I am trying to create a task in a project from the Create Record module, but the module will not populate the Planned Hours or Duration if the Task Duration Type is Simple. If unselect Duration Type it allows me to set the Duration of the task but not the Planned Hours. What do I need to do?
The following is our PTO request process: Does anyone have a similar process and how do you use Workfront to manage your process. How to enter your PTO: Workfront Request Time-off PTO by filling out the Time Off RequestOnce approved, mark your Time-off in Workfront - See Steps Below Click on Menu I...
At the end of last year (2022), we updated our Job Roles to align with each employee's title and hierarchy within their department (i.e., Group Director, Director, Associate Director, Senior Manager, Manager, Coordinator). Each employee's new (title-aligned) Job role was set up as their Primary Jo...
We are looking at rolling out Frame.io to use as our internal creative reviews and feedback for all video and animation projects. We want to continue to have stakeholder (internal & external) reviews happen in Workfront Proof and have Workfront track due dates. I was hoping for some ideas on how thi...
We would like to have a Workfront report that shows Hours and Revenue by a specific period in time. Meaning the amount of Planned and Actual hours and revenue entered in for a specific Month. Currently, there are reports that show total hours but not a report that shows hours and revenue for a perio...
I am creating this topic as a discussion. Thank you for the feedback.
The main reason we want the Job Role aligned closer to the user's title is to track Revenue and Actuals (burn). We have a rate card that has multiple layers of hierarchy, and we need to know what the Jr Designer did as well as...