Text Mode Reporting

Avatar

Level 7
Hi All, I am trying to write a task report that will show all tasks where the successor task is assigned to a specific team. In the standard builder I have managed to find a field that is 'Successor >> Assigned To ID' but I can't seem to manipulate this to the team. Any help is greatly appreciated! Vicky Fitzgerald Telegraph Media Group Limited
1 Reply

Avatar

Level 10
Hi Vicky, The Team ID is a different field than the Assigned To ID. Even though they both show up under an Assignment column they are two different fields. Take a look for Team ID in that Task. It's referring to the assigned team.