Hi Community,
How can I filter out resources that are no longer working on project so that I can only see resources who are currently working on the project as shown in screenshot below.
I have tried bunch of filters on the utilization screen but it doesn't seems that the filter on the utilization tab is working as expected,
Any help will be appreciated,
Views
Replies
Total Likes
I made a filter for Assignment / Planned Hours / Greater than 0 -- this seemed to work for me. What sort of errors do you get?
What Skye said…
or you could just use greater than 0