Is there a way implement Change Freeze in Workfront? It's possible to do it Microsoft Projects, which some of PMs still using in the background, but we would like to have it recorded within Workfront. Is it possible? Dagmara Garwell BAKKAVOR LTD
Change Freeze - unable users to modify/work on tasks while freeze period without any impact on timeline. Kind of locking some period in your project e.g. Christmas time. It helps to avoid any unexpected errors.Can be used also when limited resources are available during the holiday period. Hope that make sense? dags Dagmara Garwell BAKKAVOR LTD
I don't know of that capability, but I suppose the clunky way to do that would be to bulk edit the tasks in that grouping and change the sharing so only you can make changes to them. Vic Alejandro, PMP, CSM | IT | Sr. IT Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/"> http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT
Can you just (create and) change the status to Change Freeze (you could put a pending approval on it I guess, to further make your point) or are you specifically trying to stop people from being able to cheat the system by doing a hard lock? - skye
Hi Skye, Thanks for idea! I think actually creating a Status might be some option for it, as we could decide how we want that status to act. Dagmara Garwell BAKKAVOR LTD