Ability to set a Task constraint option as default for new tasks created in the projects associated with a group

Avatar

Level 3

5/7/24

As is:

The Task Constraint setting of new tasks can only be influenced indirectly using the Start Date setting, as follows:

Based on the Project Planned Date -> "As soon as possible"

Today -> "Start No Earlier Than (today)"

 

Desired:

For our Group Admins it would be useful to be able to set Task constraint options as default for the new tasks created in the projects associated with their group.

The ask is to have a setting for the "Task Constraint",  in the settings of a Group > Task & Requests Preferences > New Task Defaults section, similar to the "Duration type"