Hi 
We have a specific use case where a journey needs to occur on Monday, Wednesday, and Friday exclusively. However, the journey should not take place on Tuesday and Thursday. Is there a method to achieve this within the context of journey planning? If so, please provide the necessary steps to accomplish this task.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Employee

You can let the journey run daily and by using a condition activity, that will allow profiles to pass through only on specific days. Reference - https://experienceleague.adobe.com/docs/journey-optimizer/using/orchestrate-journeys/about-journey-b...

 

dugganab_0-1708528884580.png

 

View solution in original post

1 Reply

Avatar

Correct answer by
Employee

You can let the journey run daily and by using a condition activity, that will allow profiles to pass through only on specific days. Reference - https://experienceleague.adobe.com/docs/journey-optimizer/using/orchestrate-journeys/about-journey-b...

 