Hi,

 

I have a daily WS report (goes out as PDF) that I have scheduled for the team. Now I want to pause/ stop the report since it's no longer required. How to do that?

1 Accepted Solution

Avatar

Correct answer by
Employee Advisor

You can go to Components > Scheduled Projects, select the Project from the list and hit "Delete" button.

View solution in original post

4 Replies

Avatar

Employee

@dasparomita1984  - To stop receiving the Scheduled Projects, you need to remove your email from the Recipients.

 

Go to Analytics > Components > Scheduled Projects> Edit scheduled project > Update

 

 

metripat_0-1627518150027.png

 

Avatar

Level 1
Really helpful for updating WS scheduled reports. Thanks!

Avatar

Correct answer by
Employee Advisor

You can go to Components > Scheduled Projects, select the Project from the list and hit "Delete" button.

Avatar

Level 4

Hi,

 

Go to components ->scheduled projects->select the project and then hit delete the project.