Hi Everyone, I would like to ask some of Workfront set up issues after I have practice session with my team. Hope everyone in this group can provide me the direction/information how to resolve . Questions below: 1. Routing/Sequence if the task assigned to more than one person (e.g. Person A and B are assigned to the same task, but we want Person A to work on it 1st then pass to Person B, is there any function I can set it up?) 2. How can I setup a dashboard of "My Team on Vacation" Thanks in advance! Annie Li From Toronto Annie LI McCann Health
2 Replies

Avatar

Level 7
For question 1 it seems like that it might make sense that you separate it into two tasks and use a prerequisite to ding the next person in like that their task is ready to start Richard Carlson Behr Process Corporation

Avatar

Level 10
I think #2 was addressed in another thread (or at least some options). For #1 the way I would do it would be to create two tasks (one for Person A and one for Person B) and make Task a 1 predecessor to Task B. And if each task has an individual assigned, Person B will get an email from Workfront when Task A is completed, to let them know they can start on their portion. Vic Alejandro, PMP, CSM | IT | Sr. Technical Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/"> http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT