WorkFront calculations

Avatar

Level 1
Hi, Quick question we're struggling with. Why do we get different results for different people with all the same task settings? Constraint: As soon as possible. We dont use WF for resource leveling. Usually only scheduling and no hours. Best regards Matthijs Matthijs
2 Replies

Avatar

Level 10
Hi: Do you mean that if you assign person A to a task, the dates work out one way, and if you remove person A and instead assign Person B, the dates are different from when Person A was assigned? Things to check for: Do each of the resources you are assigning have the same schedule? Does one person have PTO defined and other does not? Thanks, Eric

Avatar

Level 1
Thanks Erik. Will check. Matthijs Matthijs