Topics help categorize Community content and increase your ability to discover relevant content.
Hi Elliot! I'll pull back the curtain a little bit to talk about how billable resources (like myself) log time at Workfront. These are the hour types that we use:
Task/Project/Issue-specific Hour Types:
Pre-paid Billable
Non-billable - Approved
Internal Task Time - Approved
General Hour Types:
General Overhead
Holiday
Internal Meeting Time
Other Leave
Product Enablement
PTO
Team Activity
Training
Travel (Customer)
Travel (Internal)
Let me know if you have questions about any of these!
Views
Replies
Total Likes
Hi Katie,
Hope you are doing well.
Appreciate the info.
Elliot
Views
Replies
Total Likes