Users are receiving Overdue Notifications on issues that have been converted to projects. Has anyone else had this experience? Users are also not able to change the status of the issue. Thanks! | Community
Skip to main content
Level 2
October 19, 2021
Solved

Users are receiving Overdue Notifications on issues that have been converted to projects. Has anyone else had this experience? Users are also not able to change the status of the issue. Thanks!

  • October 19, 2021
  • 1 reply
  • 687 views
No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by AneesahCampbell1

Hi Patrick!

Yes, I did reach out to support on this.

If the "Keep the original issue and tie its resolution to the project" box is checked in the Setup area then the original issue will always appear late based on the project due date. If this box is unchecked then the system treats the issue and project as separate objects and the due dates have no relation to one another.

Hope this helps!

1 reply

Level 2
November 17, 2021

I am also having this experience. Did you ever put in a support ticket or figure out how to mitigate the behavior? It's definitely annoying our planners in WF.

AneesahCampbell1AuthorAccepted solution
Level 2
November 17, 2021

Hi Patrick!

Yes, I did reach out to support on this.

If the "Keep the original issue and tie its resolution to the project" box is checked in the Setup area then the original issue will always appear late based on the project due date. If this box is unchecked then the system treats the issue and project as separate objects and the due dates have no relation to one another.

Hope this helps!