Question
Timeline Issues?
Hi All! Not sure if anyone else is having this problem, but I've been noticing that there are tasks in my project task lists that don't follow the timeline of tasks correctly, for example: I'll have set up the "Design layout" child task to be 1 day, and then the "Internal Review" task to be a half day. However, for some reason - even with a predecessor AND the assignee not having vacation days for this time - there is a weird three-six day gap that appears between tasks, for no discernable reason. It also occurs in our proof approval stage, where I'll set the individual stages to be 2-1 day tasks, but for some reason, the parent task marks them as taking six days. Is anyone else having this problem and know how to fix? I've had to break the cardinal rule of not setting my own dates in order to actually give accurate timelines to our clients. Any advice is greatly appreciated! Jordyn Fischer Project Coordinator Loews Hotels