Views
Replies
Total Likes
Views
Replies
Total Likes
Hi Terry, Thanks for your response. Yes, we did originally have two tasks with a dependency. The pain point internally was that the two resources couldn't collaborate on the document if they needed to chat back and forth (within WF updates). The other pain point is that once Resource A was done, they would upload the document to the task, and then a project manager would have to re-upload it to the next task so that Resource B could begin work. It didn't seem efficient or a good use of time for a project manager. Ultimately, there are pros and cons to both ways, I guess it's just which cons our internal resources are most willing to live with. Jenn Jennifer Tanabe Director, Project Management Vertical Measures
Views
Replies
Total Likes
Views
Replies
Total Likes
Views
Replies
Total Likes
Views
Replies
Total Likes