Return Date of First Hours Logged

Avatar

Level 2
Hello All, I would like to run a report that returns the date of when the first hour was logged on a project. Example, the results would look something like this: Project Name | Date that logged hours are greater then 0 | Task(s) Name(s) related to those first hours logged | Any help would be much appreciated. Thanks, Joe C.
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

0 Replies

Avatar

Level 5
Hi Joe, Start with an Hour report. You can add "Hour Entry Date" as a Column, then sort by that column in reverse chrono order. Hope that helps! Brian Brian C. Mauger Bloomberg L.P.