Hello, Since the new auto-complete functionality launched, I am no longer able to make a project that was autocompleted Active again. I tried changing some of the tasks to In Progress but it will not allow me to do so. Does anyone know how to do this? Thanks in advance! Kasey Boegler loanDepot
Have you tried Edit Project --> Setting --> Completion Mode -- changing it to Manual and then moving Project status to In Progress? Terry Hynd EBSCO Information Services