Quick Tip: How to add Portfolios and Programs columns to a Task report

Avatar

Employee

Program and Portfolio Owners as well as other stakeholders may find it helpful to group a Task report by Program or Project if, for example, they want to see all of the tasks in a specific program or portfolio that are overdue. To do this, simply edit your report, navigate to the grouping area and switch to text mode. Then paste the following code!

Group a Task Report by Portfolio:

group.0.displayname=Portfolio

group.0.valueformat=HTML

group.0.valuefield=project:portfolio:name

Group a Task Report by Program:

group.0.displayname=Program

group.0.valueformat=HTML

group.0.valuefield=project:program:name

"Like" this post if you find it helpful!👍

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 1

Hi we have several instances where either the program or portfolio is used for different purposes. Is there a way to create conditional grouping?

 

So if there is no Portfolio associated with that task it will instead pull in the Program. 

Avatar

Level 4

I think having a Program without an associated Portfolio is impossible. 

But if it is, then the grouping text mode would probably be:

 

group.0.displayname=Portfolio or Program
group.0.valueexpression=IF(ISBLANK({project}.{portfolio}.{name}),{project}.{progam}.{name},{project}.{portfolio}.{name})
group.0.valueformat=HTML
textmode=true