I'm looking to incorporate our project deliverables in Workfront. Currently we use an Excel spreadsheet with the following columns: Type of deliverable, name of deliverable, number of versions, ship date, date to IS, live date (put up/take down for web). I was thinking I could do this with a custom form; however, we have up to 100 deliverables for a project. Any ideas on the best way to incorporate this info into WF? thanks!
8 Replies

Avatar

Level 10
Hi Jan, Workfront is certainly capable of capturing the information you're tracking in Excel as custom data, and I'd encourage you to pursue that idea, since -- by having it in Workfront -- you can then get more value out of the data than you could as an attached Excel document, such as reporting on it, editing it inline, and charting it. The trick is deciding WHERE to put that custom data. Using a Goldilocks and the Three Bears analogy, here's my take: Project Level (TOO HOT): with 6 custom fields and 100 orders, you could create 600 custom fields at the Project level...but that would be very cumbersome to enter, exceed the 500 parm per form limit, and be extremely rigid and unmaintanable. Issue Level (TOO COLD): you could raise 100 Issues behind each Project, storing the 6 fields on each Issue independently. Not a bad solution (in fact, I've used this approach), but since three of your six fields are dates, my bet is that there'd be advantages to show them on a timeline, so Task Level (JUST RIGHT): if you use the Task Planned Start Date as the Ship Date (assuming that's "first"), the Live Date (assuming that's "last") as the Task Planned End Date, and the other 4 fields as Custom Form information (including the "Date to IS" as something that MUST be filled in by a certain point between the two), you can then visualize the acitivity of the first two dates over time using the Task Gantt view, and the presence (filled in) or absence (white/red if "too late") of the latter date in grid format. And edit all of the above in a Task grid view. And (if it makes sense) create a template of these 100 deliverables, so that Projects are created with all these Task "pre-loaded" for the orders. Or (if it doesn't make sense), create a template with one such Task in it (or several related Tasks in it), which can then be easily Inserted into the Project as needed. Hopefully this gives you some ideas. If you're currently working with a field support consultant from Workfront, they (knowing your business) will be in a far better position than am I to advise you, so I'd encourage you to ask them to help you make the best choice. Regards, Doug

Avatar

Level 2
Thanks, Doug. For the way we work, this info has to be at the project level. We are a creative/editorial group within the company. Our deliverables are print pieces, emails, web pages, etc. While I could upload an Excel doc to the project, I'd rather be able to input the data directly into a form.

Avatar

Level 7
I agree with Doug in that I would look seriously at doing this at the task level. Based on your last comment, I don't see anything there that says you can't do it at the task level.

Avatar

Level 2
My end result here needs to be a comprehensive list of deliverables with only the most important info about each. It has to be easily accessible (in totality) by all users. I don't understand how putting them at a task level will give me that.

Avatar

Level 7
Without knowing the full details, I was thinking you would create a task for each deliverable, and add the same custom form to each with whatever data you wanted to display. Then you could create a Filter and a View (or a report) that showed just those tasks and all the information you wanted to display. On the surface, it seems this would be a great solution.

Avatar

Level 7
Adding then that you could also track all these deliverables like any other task - when they get completed, changed, etc.

Avatar

Level 2
Oh - ok! I get it - sorry, a little slow on the uptake here. :) That just might work as I could create a separate "psuedo project" of deliverables. I'll have to put this idea out to our group to see what they think, but I'm optimistic. Thanks to all!!!

Avatar

Level 2
Just a quick follow-up: This solution worked very well! Thank you Doug & Greg!