Trying to determine exactly how the project condition gets determined. I see that the Estimated Completion date plays a part in it. And I can run a report to see that date, but I don't see how/where/when it get changed. It isn't on the project details, tasks details or issue anywhere to view?
Trying to determine the exact calculation of when/how a project goes from On Target to At Risk.
Views
Replies
Total Likes
It has to do with the critical path of the project - this page has an overview of how the status is determined.
As a former customer (now employee), because my projects often had flexibility (I could typically borrow days from other tasks, if needed)- we typically ignored the project status. If I was still a customer now, I'd remove it from our project header in the layout templates. But you can also set the condition to be updated manually, if you prefer.