Hi, I tend to do a pie chart and put percentages I have also gone a little fancy and have a calculated field that does Yes or No if the project is late and then I do a bar chart based on that The calculated field is IF(Progress Status="LT","Yes","No") (Just remember, the expression doesn't recalculate automatically, only when the project is edited. So before any presentation to executives, I do a bulk recalculate on all projects to make sure. ;) Hope this was helpful Anthony Imgrund FCB