Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!

No Dates When Tasks are In Column Heading style

Avatar

Level 10
I think I have a syntax error somewhere - but I can not find it. Please help. In the file attached (Task Report One Project At A time) - everything worked. We would change the dates right in the report, however, this is only view 1 project at a time. The tasks are in each row and it works perfectly. In trying to put those green tasks across the columns and pull up multiple projects in a report - to change them as oppose to change 1 at a time - then I get no data. (Task Report in Column view No Data) This is the text mode that I am using - Why am I getting no dates???? Thanks for help in debugging this issue. column.1.displayname=Kickoff Call Target Date column.1.listdelimiter=
column.1.listmethod=nested(tasks).lists column.1.sharecol=true column.1.textmode=true column.1.type=iterate column.1.valueexpression=IF({name}="Kickoff Call Target Date",{plannedCompletionDate}) column.1.valueformat=HTML column.2.sharecol=true column.2.textmode=true column.2.value= column.2.valueformat=HTML column.2.width=1 column.3.displayname=Kickoff Call Target Date column.3.listdelimiter=
column.3.listmethod=nested(tasks).lists column.3.textmode=true column.3.type=iterate column.3.valueexpression=IF([name}="Kickoff Call Target Date",CONCAT({percentComplete},"%")) column.3.valueformat=HTML Benetta Perry APS
9 Replies

Avatar

Level 10
I am getting some dates now but they are not inline editable. I added in this text mode line "makeFieldEditable=true" - the fields are still not editable. Benetta Perry APS

Avatar

Level 10
sorry - the project report displayed dates - not the task report - which is the report i'm working on. Benetta Perry APS

Avatar

Level 3
Hello Benetta, It looks like you have a [ instead of a { in your Col3 Value Expression If Statement. Unfortunately, even when you get this to display the task dates in the columns on a project report, the dates won't be editable as valueexpression data isn't editable. Patricia Greene JLL

Avatar

Level 10
I will make the correction, goo eye, thank you and i have produced a 'task report' not a project report - should the fields be editable this way? Thanks. Benetta Perry APS

Avatar

Level 3
I believe it's the valueexpression that is preventing it from being editable. Patricia Greene JLL

Avatar

Level 10
ok let me check this. Thanks. Benetta Perry APS

Avatar

Level 10
Hi Benetta, @Patricia Greene is correct in that valueexpressions aren't going to allow for inline edits. This line is the culprit: column.1.valueexpression=IF({name}="Kickoff Call Target Date",{plannedCompletionDate}) You'll need to use the valuefield option for inline edit-ability. Thanks, Narayan

Avatar

Level 10
Narayan, They must be editable - else this effort is a waste of time. So changing that line to valuefield. column.1.valueexpression=IF({name}="Kickoff Call Target Date",{plannedCompletionDate}) is this the new correct syntax? column.1.valuefield={"Kickoff Call Target Date", {plannedCompletionDate}) with the end result = the column would display the date value of the task "kickoff call target date" and that date would be editable. Thanks Benetta Perry APS

Avatar

Level 10
Narayan, Do I still need the IF in the syntax? Which one is correct - if either? column.1.valuefield=("Kickoff Call Target Date", {plannedCompletionDate}) column.1.valuefield=IF("Kickoff Call Target Date", {plannedCompletionDate}) Benetta Perry APS