I was having a little play around this, as one of our projects manager wanted to allocate his Planned Hours around some bucket tasks relevant with project management activities.
He's a project manager, resource manager for the project and obviously have manage access to his tasks.
The problem is he cannot modify his allocation and adjust planned hours on a given day. Did anyone come accross this problem ?
I had a look at WF Help article and it says the same:
The following types of users can view or modify user allocations in Workfront:
Resource Managers: You can view and modify user allocations for tasks and issues on any projects for which you are the Resource Manager. For information about how Resource Managers can make changes to tasks and issues across projects, see "Managing User Assignments."
All Users: You can view allocations for any tasks and issues you are assigned to by using the either calendar in your My Work area or the Working On calendar on a team that you are a member of. In addition to viewing allocations, you can modify your allocations if you have Contribute access to the tasks and issues.For more information about how to use the calendar in the My Work area, see "Viewing Assigned Work on the My Work Calendar."
Any ideas about this ?
Thanks,