Hi Md, "In Trouble" is Workfront's system generated assessment of the projected progress of the Project relative to its planned progress, and is intended to give (early) warning to Project Managers (et al) that things are starting to slip. The Project's Status (Complete, in your example) is separate, and typically driven by the Project's underlying Tasks: namely, once they are complete, so is the Project. Your screenshot, then, illustrates to me that the Project is Complete, but that when it did finish, it was In Trouble. Regards,
Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand!