How might a Commit Date have been entered on a Task if not by the Task Assignee?
I have a user (project manager) who found that her Projected Completion Date of a project was way beyond the Planned Completion Date, and I can see that there are quite a few Tasks with Commit Dates beyond the Planned Completion Dates for those tasks, so that tells me this is what's driving it. However the project manager swears she did not enter the Commit Dates. As she's the assignee for all of those tasks, is there some other way they could have been populated?