One of my favorite columns to add to project reports:
Current Task - Show which task is currently being worked in the project
displayname=Current Task
listdelimiter=< p >
listmethod=nested(tasks).lists
textmode=true
type=iterate
valueexpression=IF({numberOfChildren}=0,IF({canStart},IF(CONTAINS("CPL",{status}),"",CONCAT({name}," "))))
valueformat=HTML
Current Task - With Planned Completion Date
valueexpression=IF({numberOfChildren}=0,IF({canStart},IF(CONTAINS("CPL",{status}),"",CONCAT({name}," - ",{plannedCompletionDate}))))
listdelimiter=& z w j ;
listmethod=nested(tasks).lists
valueformat=HTML
displayname=Current Task
textmode=true
type=iterate -- Melinda Layten, Senior Consultant Work Management Improvement CapabilitySource - 2018 Workfront Services Partner of the Year Phone: (484) 505-6855 site: