This is a challenging one, isn’t it? I’m not using Text Mode, I’m not that skilled. The problem is you can’t look at the Assignment table, because there should be no rows in that table if there are no assignments. You can’t filter the table on all projects that have no assignments. There is nothing there to filter. You have to look at the task object. You’re looking for a task where there is no user, no role, and no team assigned. The assignments aren’t easily filtered at the task object. Here is the filter criteria I used to identify all tasks (there are criteria above that select my special play project with test data in it): [cid:image001.jpg@01D1B67A.A7A3F2E0] Why does this work? At the task level, WorkFront keeps track of the primary user / role assigned to the task. It does not allow a team assignment to be primary. Therefore, if the assigned to ID is blank, then the task isn’t assigned to a user. If the primary user role ID is blank, it isn’t assigned to a role. If the Team ID is blank, it isn’t assigned to a team. I think that is what you’re looking for - let me know if it isn’t. Thanks! Eric